Required Documents for Prior Child Development Division Approval of Subcontracts.   

arrow Previous bar Next arrow

The contractor shall submit the following documents to the Child Development Division before entering into any agreement with a proposed subcontractor and before any work begins pursuant to the proposed subcontract:

(a) A copy of each bid or estimate

(b) If applicable, the documents required to be maintained under Section 18027(b) of this Division;

(c) Identification of the lowest responsible bidder selected by the contractor

(d) For capital outlay subcontracts, documents showing that the bidder selected by the contractor has obtained a payment bond in an amount not less than one-half (I/2) the amount of the proposed subcontract; and

(e) Two (2) copies of the proposed subcontract, including a proposed line item budget which shows the costs of the services to be performed. The budget for a proposed subcontract for renovation and repair shall show the total cost of labor and the total cost of materials.

Authority and Refeence Cited:

Education Code 8261