Environmental impact report and environmental impact statement   

arrow Previous bar Next arrow

In the event that a project requires both an environmental impact report prepared pursuant to the requirements of this division and an environmental impact statement prepared pursuant to the requirements of the National Environmental Policy Act of 1969, an applicant may request and the lead agency may waive the time limits established pursuant to Section 21100.2 or 21151.5 if it finds that additional time is required to prepare a combined environmental impact report-environmental impact statement and that the time required to prepare such a combined document would be shorter than that required to prepare each document separately.

(Added by Stats. 1977, Ch. 1200, Sec. 8.)